XP Home

Iteration Planning

 

 An iteration planning meeting is called at the beginning of each iteration to produce that iteration's plan of programming tasks. Each iteration is 1 to 3 weeks long. User stories are chosen for this iteration by the customer from the release plan in order of the most valuable to the customer first. Failed acceptance tests to be fixed are also selected.
 The user stories and failed tests are translated into the programming tasks that will support them. Tasks are written down on cards. These task cards will be the detailed plan for the iteration.
 Each task should be 1 to 3 ideal programming days in duration. Ideal programming days are how long it would take you to complete the task if there were no distractions. Tasks which are shorter than 1 day can be grouped together. Tasks which are longer than 3 days should be broken down farther.
 Developers sign up for the tasks and then estimate how long their own tasks will take to complete. It is important for the developer who accepts a task to also be the one who estimates how long it will take to finish.
 The project velocity is used to determine if the iteration is over booked or not. Total up the time estimate in ideal programming days of the tasks, this must not exceed the project velocity from the previous iteration. If the iteration has too much then the customer must choose user stories to be put off until a later iteration (snow plowing).
 If the iteration has too little then another story can be accepted. The velocity in task days (iteration planning) overrides the velocity in story weeks (release planning) as it is more accurate.

 It is often alarming to see user stories being snow plowed. Don't panic. Remember the importance of unit testing and refactoring. A debt in either of these areas will slow you down. Avoid adding any functionality before it is scheduled. Just add what you need for today. Adding anything extra will slow you down.
 Don't be tempted into changing your task and story estimates. The planning process relies on the cold reality of consistent estimates, fudging them to be a little lower creates more problems.
 Keep an eye on your project velocity and snow plowing. You may need to re-estimate all the stories and re-negotiate the release plan every three to five iterations, this is normal. So long as you always implement the most valuable stories first you will always be doing as much as possible for your customers and management.
 An iterative development style can add agility to your development process. Try just in time planning by not planning specific programming tasks farther ahead than the current iteration.Move People Around